2024年10月18日
遺產規劃及遺囑信託
A recent BC Supreme Court case, Zheng v. Anderson Square Holdings Ltd., 2024 BCSC 216, highlights the many pitfalls that await both pre-sale purchasers and developers alike in the high stakes world of real estate development. For pre-sale purchasers, what happens when developers give them notice, years after contracts have been signed and deposits paid, that the project cannot continue on for a variety of reasons, that their contract is thereby cancelled, and that the only remedy they have is that their deposits were being returned, albeit with interest?
For developers, what happens when their main building contractor demands additional payments for their construction costs, stops work and then sues the developer for these additional costs part way through the construction?
The Zheng case has all of this, but is replete with so many twists and turns along the way that it is worthy of its own soap opera.
To summarize, in 2015 and 2016, Anderson Square Holdings, the Developer, developed, marketed, and sold units in a presale project in Richmond called “The Alfa”, consisting of 109 residential strata units and 10 commercial strata lots.
In July 12, 2019, Anderson notified its buyers through Termination Notices that they were terminating their contracts – as provided for under the terms of their contracts - and offered them a return of their deposits.
Besides construction delays, two other reasons were cited by Anderson:
(1) a lawsuit filed against them by their building contractors, and
(2) the failure of their efforts to secure construction financing.
37 of the buyers refused to accept the fact that the their contracts were cancelled and rejected the return of the Deposits.
Two years later the project was completed and the units were remarketed as “The Prima” and sold to new purchasers at higher prices. Zheng was the outcome of the lawsuits filed by the 37 disgruntled purchasers, where the Court awarded the plaintiffs $13,093,900 collectively in damages, based on the difference between the prices that the units were originally sold for and their value in August 2021 when the disgruntled purchasers sued the developer.
An account of some of the most important details of this case:
1. The purported inability of the Developer to obtain financing because of a lawsuit by its own building contractors was found to be a half-truth at best, because (a) the failure to obtain institutional financing pre-existed the date of the lawsuit, and (b) there was evidence of private financing not only being made available, but being advanced, allowing construction to continue even after the Termination Notices of 2019;
2. The purported economic effect of the lawsuit on the Developer by its own building contractors was also found to be a half truth as well, because basically a lawsuit is not a judgment, but only an allegation that has yet to be proven in court, especially since the construction contract was a “fixed price” contract.
3. The wording of the individual Contracts regarding the Developer’s right to terminate the Contract, especially the use of two little words – “provided that” - was ambiguous, because while one clause seemed to automatically extended the completion date, the other clause seemed to limit it, and so when read overall in the context of the entire contract, it was more correct to say that the completion date was automatically extended and therefore the Developer did not, after all, have the right to terminate.
4. When faced with a termination notice, the purchase has two options - to accept what is legally called a “repudiation of the contract,” take back the deposit, and consider the contract “ended” or to refuse to accept the contract as having ended, treat the contract as still alive, and insist on a completion until it is no longer possible to do so, which in this case was August 2021 when Alfa was being resold as Prima, and the purchasers sued, thereby ending the contract at that time
What lessons can be learned?
Both from a legal standpoint and also from the standpoint of the individual pre-sale purchaser or developers - when faced with such a predicament.
Firstly, for Developers, when stating the reasons for termination of their presales contracts, those reasons better be accurate and be built on a solid foundation of reliable evidence. Secondly, for presale purchasers, when facing a Developer opting to cancel their projects, there is hope for alternative outcomes other than just the return of their deposits, but it may take lots of time – in this case almost eight years – and the combined financial resources of 37 plaintiffs to get to this outcome.
Secondly, for real estate lawyers acting for developers or representing disgruntled pre-sale buyers, it pays to be precise, careful, and mindful of cases such as Zheng.
Case Commentary provided by Real Estate Law Specialist, Iven Tse. Call him today to represent you!
IVEN K. S. TSE LAW CORPORATION
Barrister and Solicitor, Notary Public
#M2A - 601 West Broadway, Vancouver, BC V5Z 4C2
Tel: (604) 877-2686
Check out Iven’s CHMB 1320 AM Cantonese Radio “Legal Hotline” podcasts on youtube: https://www.youtube.com/results?search_query=iven+tse+law
DELLA GOUGH
della@dellacarolynrealtors.com
604-889-3811
CAROLYN RUTHERFORD
carolyn@dellacarolynrealtors.com
778-951-6749
READY TO MAKE A MOVE?
We would love to be your agents of choice. You only get one chance to sell your property and we know how to do it! It would be our privilege to market your property and help you maximize your profits. CALL US TODAY!